The NHAI that is executing the six-lane new bridge across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 is hopeful of commissioning the new briege by end of May 2026, as the Authority is counting days to launch girders at Kulur, on January 8, in Mangaluru.

The NHAI that is executing the six-lane new bridge across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 is hopeful of commissioning the new briege by end of May 2026, as the Authority is counting days to launch girders at Kulur, on January 8, in Mangaluru.
| Photo Credit: H S MANJUNATH

After missing multiple deadlines to commission the new six-lane bridge at Kulur during the last three years, the National Highways Authority of India (NHAI) is hopeful of completing the project before the onset of 2026 monsoon.

The Authority has planned the new bridge across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 as a part of widening of the B.C. Road-Surathkal Port Connectivity Road into six lane. The work was awarded to Pune-based M/s Shinde Developers Pvt. Ltd., at a cost of ₹56 crore and the actual work commenced on April 12, 2021. Though the new bridge was expected to be completed by October 2022, the project was delayed for over three years.

New Kulur Bridge across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 in Mangaluru

Number of Lanes: 2+2 for main carriageway and 1+1 for service roads

Total Length: 776 metres

Total width: 42 metres

Number of vents: 6

Main carriageway width: 14+14 metres

Service roads’ width: 7+7 metres

Awarded cost: ₹56 crore

Total capital cost: ₹69.02 crore

Actual start date: April 12, 2021

Scheduled completion date: October 11, 2022

Likely completion date: May 31, 2025

Source: National Highways Authority of India

Old bridge dilapidated

The Old Kulur Bridge commissioned in 1952 by the then State of Madras is in an almost dilapidated state and the NHAI had recommended to the district administration to close the same for traffic in 2019 itself. However, with no alternative available and the completion of the new six-lane bridge getting delayed, the old bow-string bridge continues to be in service for traffic from Udupi towards Mangaluru, thereby exposing users to danger.

One pier cap pending

Pier caps for all but one of the six piers are complete for the six-lane new bridge being built by the National Highways Authority of India (NHAI) across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 at Kulur.

Pier caps for all but one of the six piers are complete for the six-lane new bridge being built by the National Highways Authority of India (NHAI) across Phalguni (Gurupura) River on Kanniyakumari-Panvel National Highway 66 at Kulur.
| Photo Credit:
H S MANJUNATH

NHAI Mangaluru Project Director Abudlla Javed Azmi told The Hindu that pier cap for all the piers, but for one, was complete and the pending cap would be completed within a few days.

Casting of girders was underway at the contractor’s facility in Panambur with about 60 girders ready for launch. The Authority was hopeful of commissioning the new bridge before the onset of monsoon in 2026, the officer said.

42 m wide

The structure would be 42-metre wide in total with provision for service roads on both the sides and two main carriageways of two lanes, each of 7-metre width. Along the service roads, provision would be made for pedestrian path also, Mr. Azmi said.

The old bow-string bridge across Phalguni (Gurupura) River built by the then Highway Department of Madras State in 1952 on the present Kanniyakumari-Panvel National Highway 66 at Kulur will be closed for traffic once the new six-lane bridge is commissioned, the NHSI said on January 8, in Mangaluru. 

The old bow-string bridge across Phalguni (Gurupura) River built by the then Highway Department of Madras State in 1952 on the present Kanniyakumari-Panvel National Highway 66 at Kulur will be closed for traffic once the new six-lane bridge is commissioned, the NHSI said on January 8, in Mangaluru. 
| Photo Credit:
H S MANJUNATH

Once the new six-lane bridge is commissioned, the NHAI will shut the old bridge for vehicular traffic. Utility lines, including water and power, presently passing on the existing bridge, would be shifted on the closed bridge, he added.


Leave a Reply

Your email address will not be published. Required fields are marked *