According to Priyank Kharge, 32 private data centres are currently functioning in the State. | Photo Credit: PHOTO FOR REPRESENTATIONAL PURPOSE Amid concerns over environmental costs, particularly water and energy consumption, Karnataka is reviewing its policy on data centres, IT/BT Minister Priyank Kharge informed the State Legislative Assembly on Wednesday. Explaining the costs involved in establishing data centres, Mr. Kharge said around ₹70 crore is required to set up one megawatt data centre, and the total power usage, including cooling/infrastructure, is about 1.7 MW of power. About 25 million litres of water per year is required for one MW data centre. However, the actual cost depends on the location and land cost, sources said. However, he noted that new technologies are emerging that enable the use of treated water in data centres. “We have to relook at our policy, which is 2 to 3 years old,” he said Replying to a question from Dheeraj Muniraju of the BJP from Doddaballapur, Mr. Kharge said that 32 private data centres are currently functioning in the State. “We already have a data centre policy, which we are reviewing,” he added. ‘Necessary evil’ Describing data centres as a “necessary evil”, the Minister said they are essential for artificial intelligence, machine learning and other emerging technologies, but they also consume large quantities of water and energy. Earlier, Mr. Muniraju said Bengaluru was losing out on data centre investments as companies were moving to other Indian cities. Bengaluru currently ranks fifth among Indian cities for data centres, after Mumbai, Hyderabad, Chennai and Delhi, he said. Mr. Muniraju noted that several global technology firms have offices in Bengaluru and suggested that their data centres should be retained in the city. Sustainable policy Mr. Kharge said the government is working towards a “sustainable data centre” policy and that the focus would be on Mangaluru and other coastal areas. “Hyperscale data centres may not be suitable for Bengaluru, which does not have a port and lacks abundant water resources,” he said. Data centres requiring more than 40 MW of power would fall under the hyperscale category, he added. The Minister also said discussions were under way with private companies on laying subsea cables in the coastal region. He had written to the Union Telecom Ministry seeking a subsea cable landing station in Mangaluru, and the Ministry had responded positively, stating it would extend support if private companies took up the implementation. Published – March 11, 2026 07:58 pm IST Share this: Click to share on WhatsApp (Opens in new window) WhatsApp Click to share on Facebook (Opens in new window) Facebook Click to share on Threads (Opens in new window) Threads Click to share on X (Opens in new window) X Click to share on Telegram (Opens in new window) Telegram Click to share on LinkedIn (Opens in new window) LinkedIn Click to share on Pinterest (Opens in new window) Pinterest Click to email a link to a friend (Opens in new window) Email More Click to print (Opens in new window) Print Click to share on Reddit (Opens in new window) Reddit Click to share on Tumblr (Opens in new window) Tumblr Click to share on Pocket (Opens in new window) Pocket Click to share on Mastodon (Opens in new window) Mastodon Click to share on Nextdoor (Opens in new window) Nextdoor Click to share on Bluesky (Opens in new window) Bluesky Like this:Like Loading... Post navigation ED searches 19 locations in Haryana, Chandigarh in ₹590 crore IDFC First bank ‘fraud’ case Secondary School Leaving Certificate examination begins in southern districts